Progress on electric continues. We'll be needing to provision for the transfer switch, but all in all, having a service panel in place is a good start!
We have a fair bit of rework to do as Jim located double electric boxes to contain two devices (eg: two switches, or two outlets) at once. This to make the inside wall finish easier, and electric things more organized.
We also dropped one "requirement", and will eliminate the two ceiling fans in the 'cupola'. After all, that is really intended to be a natural feature to manage cooling naturally.
We included this photo of one of the lower bedrooms. That big X you see is more wall area. But gives a nice idea what the light and view is like down on that level. Should be fantastic as the monkeys come through!
As you can see in this third photo, Alvarro is fitting in exterior fibroleit against bathroom #2, the one adjacent to the stairs that will go up to the main level. Our plan is to cover that overhang with teak to make that
While this final view doesn't show the whole structure, it does show the lower corner next to where the stairs will head up. That large opening above their heads still needs the window framed in, but for now is still the access to get to the second floor. Hopefully stairs can start 'soon'. That little window on the right just over the guys heads is the one over that
So friends, we do encourage comments.
Meanwhile that's it for this post. Thanks for reading!